Ikeja Electric Prepares Lagos For 8weeks Power Shutdown

Lagos State residents, particularly those settled in Ikeja axis of the state, would be experiencing power shutdown for a period of eight weeks as part of repair work that would be embarked on by the Transmission Company of Nigeria (TCN)

 

As gathered, the area that would be affected during the shutdown to enable the Transmission Company of Nigeria, TCN, re-conduct its 132KV lines include Oregun, Police Training College, Oba Akran, Oke Ira, Ogba, Magodo, Anifowoshe and Omole Phase One.

 

Confirming the development, the Ikeja Electric Plc, Chief Technical Officer, Olajide Kumapayi, said that the project, which would begin on October 11, was aimed at increasing the capacity of the transmission lines to wheel more power from the generation companies.

 

Briefing journalists on Monday on the TCN motives, he noted that some of 132K lines installed over 50 years ago had become obsolete and degraded due to time and usage, hence the need for the upgrade.

 

According to him, the TCN is currently embarking on the upgrade of the 132KV lines from Ikeja West to Ota and Alimosho in stages. This is the second stage.

 

“The TCN is replacing all the aluminum conductors with gap conductors which is more sophisticated to withstand heat and has more capacity to carry current.

 

“The implication of this is that from 8a.m. to 6p.m. everyday, the substations controlling these areas will be switched off, which will affect the feeders connected to them.

 

“This will affect all categories of customers within the area especially our Maximum Demand (MD) customers such as Ikeja City Mall, Police College, Lagos State University Teaching Hospital and the Ikeja High Court.”

 

He added that the TCN would also move to Alimosho and Agege axis during the next stage, noting that the upgrade was a power sector initiative to boost transmission and distribution of electricity to Nigerians.

 

On his part, the company’s Head, Corporate Communications, Felix Ofulue, said that the DisCo had written to the MD customers notifying them of the situation, adding that the company was also meeting with its bilateral power supply agreement partners and appealed to all those affected to exercise patience with the DisCo during the period.

 

“Even though this is a TCN project, it is our duty to inform our customers of the situation because we are the ones that interface with them on a daily basis.

 

“We believe it will be for the benefit of our customers at the end of the day and will also allow Ikeja Electric to invest more in our system to improve power supply to customers under our network,” Ofulue said.